BP Quad 204
BP Quad 204
With an integrated approach to the design and delivery of complex programmes, we successfully worked with BP to manufacture 73 modules for its Quad 204 project – one of the largest ever subsea fabrication orders placed in the UK.
Delivered 100% to schedule, the programme relied heavily on Babcock’s ability to manage large-scale projects, carry out precise engineering and assembly, and to work collaboratively with its customer and sub-contractors. Our scope of work included detailed fabrication engineering, material procurement, fabrication and assembly, control’s fit-out support, factory acceptance testing, system integration testing and load-out support.
The quantity and scale of the structures required a carefully planned facility solution, which we developed with our proven Project Management experience.
Our customers draw on our long-standing experience to drive their programmes forward and to help them meet stringent schedules, quality and safety standards.